N1.C
Find a section, then divide it in the right order
A standard township contains 36 numbered sections. Section 1 is at the northeast corner. The first row runs west to Section 6, the next row runs east from 7 to 12, and the rows snake back and forth to Section 36 at the southeast corner. The northwest corner is Section 6.
A regular section is one square mile, or 640 acres. Half is 320 acres, a quarter is 160, and a quarter of a quarter is 40. For E 1/2 of SW 1/4, start with the whole section, find its southwest quarter, then take the east half of that quarter: 640 × 1/4 × 1/2 = 80 acres.
Multiplying gives you area; the compass letters give you location. NE 1/4 of SW 1/4 and SW 1/4 of NE 1/4 each contain 40 acres in a regular section, but they’re in different places. Read the description from the end (the largest piece) back toward the beginning. Use the surveyed acreage when a question gives you an irregular section or a government lot.
Choose a description. Start with the whole section, then follow each smaller part. Compare the two 40-acre examples.
E 1/2 of SW 1/4: 80 acres
- Start with the whole 640-acre section.
- Find the southwest quarter, containing 160 acres.
- Take the east half within that southwest quarter.
640 × 1/4 × 1/2 = 80 acres
Assumes a regular 640-acre section. Equal acreage does not mean the same location. Use actual survey data for irregular sections and government lots.
Work the example
A problem specifies a regular 640-acre section and asks for the area of its southeast quarter’s west half.
How many acres are described?
Show answer and reasoning
80 acres.
640 × 1/4 × 1/2 = 80. The west half is taken within the southeast quarter.
Section = 640 acres. Multiply the fractions; read the letters for location.
Sources and full lesson context
- Federal source43 U.S.C. § 751, federal survey framework
- Federal sourceBLM, Specifications for Descriptions of Land
- Federal sourceBLM, Cadastral Surveying classroom guide
Last reviewed November 15, 2026.
N1.C
Surveys show location; title work shows rights
A boundary survey ties the legal description and boundary evidence to the ground. Depending on its scope, it may show monuments, boundary lines, improvements, access and apparent encroachments. Read its date, certification, legend and scope; not every survey answers every question.
A county GIS map or aerial overlay is handy for orientation, but it isn’t a boundary survey. Map layers are often offset, and a drawn line doesn’t decide who owns a disputed strip. A mortgage location report also has a narrower scope than a boundary survey.
Survey and title review work together. The title search may turn up a recorded easement; the survey can show where it lies. Neither an agent’s eyeball estimate nor a survey decides every legal right. If a garage seems to cross the line, bring in a surveyor and the title company before telling the buyer it’s harmless.
Work the example
An aerial tax-map line appears to pass through a neighbor’s shed.
What should happen next?
Show answer and reasoning
Check the deed and boundary evidence and get a survey before anyone draws conclusions about ownership.
GIS can’t replace boundary and title work.
GIS maps help you look. A survey locates the line.
Sources and full lesson context
- Federal sourceUSGS, why mapped PLSS lines are not a legal survey record
- Federal sourceBLM, Specifications for Descriptions of Land